Commencement of Ulog hydropower plant construction

The Contract for Engineering, Procurement and Construction of 35 MW HPP Ulog, signed between EFT HE Ulog d.o.o. and Sinohydro Corporation Ltd, has entered into force on 20 December 2019.   

Civil works are scheduled to commence in the second quarter of 2020, upon completion of Contractor’s mobilization on site. Time for completion of HPP Ulog construction is 42 months.

Supervision of construction works will be performed by Stucky Balkans, member of the Swiss Gruner Group. 

Total project capex is BAM 150 million.